PV service

How we prevented daily losses of 60 000CZK

1MW PV outage in Slovakia, June 2017 The power station was disconnected from the grid for 2 hours before technicians arranged for it to be reconnected. Thanks to online monitoring, the outage was detected almost immediately. Electricity loss in 2 hours = 1 032kWh Financial loss for 2 hours = 10 320 CZK/408 EUR

Sample losses that could occur without monitoring:

Disconnection 1 day – power loss: 5.67 MWH, financial loss: 56 796 CZK/2 245 EUR Disconnection 7 days – power loss: 39.75 MWH, financial loss: 397 500 CZK/15 712 EUR (losses are based on the purchase price of 10 016 CZK/MWh) Price of monitoring within the complete service: 200 CZK/8 EUR per day